Practical Advice: COVID-19's Impact on the Construction Industry

Client Alert

As a member of the American Bar Association, Forum on the Construction Industry, BMD participated in a COVID-19 Construction Leadership Roundtable discussion with over 450 other construction attorneys representing nearly every voice in the industry. Here is the top practical advice and key takeaways: 

  1. Safety. Safety is the overriding imperative on all construction projects. Employers should designate and empower a COVID-19 Compliance Coordinator and post on site the CDC guidelines in English and other appropriate languages. The six-foot social distancing requirement, portable handwashing, wearing gloves, prohibiting carpooling to the jobsite, and closing jobsites to the public are now considered best practices and mandatory expectations for all employers. In some states, governmental agencies are spot checking jobsites and removing individuals who are not in compliance with the CDC guidelines. The Occupational Safety and Health Administration has issued guidance for protecting employees against workplace exposures to COVID-19. Employers should also be aware of OSHA standards which may apply to workplace exposures and when a case of COVID-19 is OSHA recordable. Learn more here from BMD’s March 20, 2020 OSHA and COVID-19: Workplace Exposures, Citations and Recording Client Advisory. 
  1. Notice. Give notice early and often! After providing notice, follow up with timely reports, cost information and detailed schedule impact data. Maintain detailed records if you want to preserve any chance of recovering for delay impacts. It is not enough to generally argue that your work has been delayed by COVID-19. It must be written in a way to prevent or discourage escalation, including litigation. Be prepared to demonstrate how and when delay impacts occurred, such as utilization of a measured mile analysis to prove loss of efficiency and productivity. Helping the owner or general contractor understand the unique circumstances which caused the delay will increase your chances to cooperatively resolve the problem. 
  1. Suspension or Termination of Work. Suspension or termination of work remains an option on a case-by-case basis. Work is generally proceeding but is being impacted by CDC guidelines. Each project is unique and requires the owner’s willingness to work with prime contractors, subcontractors, suppliers, and design professionals. It has been rare for attorneys to counsel clients to stop work. There have been some suspensions of work, but often work resumes if employers and workers take appropriate CDC precautions. For example, work is proceeding at the City of Tampa, Florida airport where virtual inspections are being conducted by using affidavits, video or digital images, or in-person inspections per CDC guidelines. Some third-party inspections have been allowed and some government agencies are deferring inspections. Materials onsite are being sanitized. By contrast, due to the large number of coronavirus cases in New York and New Jersey, most private and public construction projects in those areas have been shut down. 
  1. Collaboration. Because the phrase “unchartered waters” does not begin to describe the impact that COVID-19 is having on construction projects, the best advice for prime contractors and subcontractors is to try to row in the same direction. This is no time for battles or disputes between general contractors and subcontractors. Prime contractors should ascertain the cash flow status of their subcontractors to determine whether they will be able to perform under the current revenue-starved environment. A key element for project success is that all parties need to work together to identify risks, loss of productivity, schedule impacts, supply chain issues, safety issues, etc. In fact, it has been perceived that many owners are being more forgiving on product substitutions and developing creative solutions to deal with impacts resulting from coronavirus delays – so take advantage of it while you can by being collaborative! 
  1. Liquidated Damages, Force Majeure, and Excusable Delays. How courts will interpret construction contract delay clauses, force majeure clauses and common law rights with respect to the delay impacts associated with COVID-19 remains to be seen, and it will likely be determined on a case-by-case basis. Because many courts are holding civil disputes in abeyance, immediate relief from the judicial system is unlikely. For this reason, as well as solid business judgment, it makes good sense for the parties to cooperatively engage in direct and timely discussions regarding how to proceed with construction and manage delay impacts in a mutually beneficial way. Issuance of change orders or schedule extensions may relieve some of the time and cost impacts. Prudent owners welcome timely notice because they can attempt to manage these issues and risks. Excellent communication is the key to identify problems. Deliver timely written notice and detailed substantive documentation, offer creative solutions, and try to manage the difficult circumstances together. Rather than pulling the trigger on default clauses, it is generally advisable to push across the project finish line and properly document all cost and time impacts. As we advised in the BMD Client Advisory on March 17th, the extent to which COVID-19 excuses or extends contractual obligation(s) is a fact-specific determination that will depend on the nature of the obligations and the specific language of the contract. 
  1. Project Financing. “Cash is king,” and if the availability of private and public funding is impaired, work may cease and sureties may be required to take over on payment and performance bonded projects. Conduct adequate due diligence before committing to business relationships. On an ongoing basis, be sure to request and receive adequate assurances of financial ability to pay whenever possible. 

Please feel free to reach out to Bob Hager, Justin Alaburda, David Scott, Jeff Miller, Steve Matasich or Brandon Pauley if you have any questions or comments on these issues. This is intended as general advice and should not be interpreted as legal advice. Each situation is unique and requires specific analysis of relevant contracts, facts and legal obligations.


Florida's Recent Ruling on Arbitration Clauses

Florida’s recent ruling on arbitration clauses provides a crucial distinction in determining whether such clauses are void as against public policy and providers may have the opportunity to include arbitration clauses in their patient consent forms. On March 6, 2024, Florida’s Fourth District Court of Appeals reversed and remanded Florida’s Fifteenth Circuit Court ruling of Piero Palacios v. Sharnice Lawson. The Court of Appeals ruled that the parties’ arbitration agreement did not contradict the Legislature’s intent of Florida’s Medical Malpractice Act (the “MMA”), but rather reflects the parties’ choice to arbitrate claims entirely outside of the MMA’s framework. Therefore, the Court found that the agreement was not void as against public policy.

Corporate Transparency Act Update 3/14/24

On March 1, 2024, a federal district court in the Northern District of Alabama concluded that the Corporate Transparency Act (“CTA”) exceeded Congressional powers and enjoined the Department of the Treasury from enforcing the CTA against the plaintiffs. National Small Business United v. Yellen, No. 5:22-cv-01448 (N.D. Ala.). On March 11, 2024, the U.S. Department of Justice appealed the district court’s decision to the Eleventh Circuit Court of Appeals.

The Ohio State University Launches Its Accelerated Bachelor of Science in Nursing Program

In response to Ohio’s nursing shortage, The Ohio State University College of Nursing is accepting applications for its new Accelerated Bachelor of Science in Nursing program (aBSN). Created for students with a bachelor’s degree in non-nursing fields, the aBSN allows such students to obtain their nursing degree within 18 months. All aBSN students will participate in high-quality coursework and gain valuable clinical experience. Upon completion of the program, graduates will be eligible to take the State Board, National Council of Licensure Exam for Registered Nursing (NCLEX-RN).

Another Transparency Obligation: The FinCEN Beneficial Ownership Information Reporting Requirements

Many physician practices and healthcare businesses are facing a new set of federal transparency requirements that require action now. The U.S. Department of Treasury Financial Crimes Enforcement Network (“FinCEN”) Beneficial Ownership Information Reporting Requirements (the “Rule”), which was promulgated pursuant to the 2021 bipartisan Corporate Transparency Act, is intended to help curb illegal finance and other impermissible activity in the United States.

“In for a Penny, in for a Pound” is No Longer the Case for Florida Lawyers

On April 1, 2024, newly adopted Rule 1.041 to the Florida Rules of Civil Procedures goes into effect which creates a procedure for an attorney to appear in a limited manner in civil proceedings.  Currently, when a Florida attorney appears in a civil proceeding, he or she is reasonable for handling all aspects of the case for their client.  This new rule authorizes an attorney to file a notice limiting the attorney’s appearance to particular proceedings or specified matters prior to any appearance before the court.  For example, an attorney can now appear for the limited purpose of filing and arguing a motion to dismiss.  Once the motion to dismiss is heard by the court, the attorney may file a notice of termination of limited appearance and will have no further obligations in the case.